Woodward Spartanburg Campus Fact Sheet

English | Español


Early November 2026

Main building substantially completed; capital equipment installation begins.

December 2026 to January 2027

Worksite preparation and workstation setup.

Jan. 8, 2027

Certificate of occupancy planned; team member move-in begins.

March 2027

Machine testing and verification starts.

June 2027

First qualification unit targeted.

Early 2028

Certification slated.

Mid-2029

Production planned.